For London property owners, landlords, managing agents and facilities teams, the terms asbestos register and asbestos management plan are often used together. They are not the same document. The register records where known or presumed asbestos-containing materials (ACMs) are and their condition; the management plan sets out how the risks will actually be controlled.

Under Regulation 4 of the Control of Asbestos Regulations 2012, the duty to manage applies to non-domestic premises and to the common parts of some multi-occupancy domestic premises. HSE guidance requires dutyholders to keep an asbestos record or register up to date, assess the risk, prepare and implement a management plan, monitor ACMs and provide relevant information to people who may disturb them. This article reflects HSE guidance available in September 2026.

Surveyor reviewing an asbestos register and management plan in a London commercial property
The asbestos register records the known or presumed ACMs; the management plan sets out how those risks will be controlled.

Asbestos register vs management plan: the short answer

DocumentMain purposeTypical contents
Asbestos registerA live record of known and presumed ACMs and their risk information.Location, material type, extent, condition, inspection dates, material and priority assessments, inaccessible or presumed areas, actions and updates.
Asbestos management planThe site-specific system for managing the risks identified in the register.Responsible people, monitoring schedule, access to the register, controls for maintenance work, communication arrangements, action priorities and emergency procedures.

HSE describes the asbestos register as a key part of the management plan. In practical terms, the register answers “where is the asbestos and what condition is it in?” The management plan answers “what are we going to do about it, who is responsible and how will we stop it being disturbed?”

What should an asbestos register contain?

The register should be built from reliable survey information and kept as a live document. HSE says it should contain current information on the presence and condition of ACMs or materials presumed to contain asbestos. For a London office, shop, warehouse, school, communal block or other managed premises, a useful register should allow someone planning maintenance work to identify relevant asbestos information quickly.

  • All known and presumed ACMs in the areas covered by the duty to manage
  • The asbestos-containing product or material type
  • The amount or extent and current condition
  • The date of the original inspection and the latest condition check
  • A material assessment and a priority assessment or equivalent risk evaluation
  • Any areas that were not inspected and where asbestos must therefore be presumed where appropriate
  • Actions, due dates and evidence of completed actions
  • Updates when ACMs are repaired, encapsulated, removed, newly identified or affected by a change in use

HSE states that the register should be updated at least once a year as part of the asbestos management review, and sooner where something changes the risk. That could include damage, refurbishment, removal work, a new survey, a room-use change or maintenance that increases the likelihood of disturbance. See our asbestos register guidance for more practical information.

What should an asbestos management plan contain?

A management plan goes beyond recording asbestos. It sets out the procedures and responsibilities that turn the register into an operating control system. HSE guidance says the plan should be site-specific, easy to find and update, and clear about who is responsible for each part.

  • The person responsible for managing asbestos and suitable deputies
  • The asbestos register and site plan, including areas that were not inspected
  • The schedule for monitoring the condition of ACMs
  • How the register will be shared with employees, maintenance workers and contractors
  • Controls to prevent ACMs being disturbed during routine and planned work
  • Priorities for repair, encapsulation, removal or continued management in place
  • Emergency arrangements if asbestos is accidentally damaged or disturbed
  • A process for recording completed actions and reviewing whether controls remain effective

The plan should not exist only as a file on a server. It needs to be used before work starts. HSE says workers and contractors who may disturb the building fabric must receive relevant asbestos information before they begin. For planned work, this information should be provided as early as possible, for example when quotations are being requested.

Property manager reviewing asbestos register and management plan records
A management plan should connect asbestos information with responsibilities, maintenance controls, monitoring and contractor communication.

How the survey, register and management plan fit together

These three elements should be treated as a chain rather than separate paperwork. A suitable asbestos survey provides information about ACMs. That information feeds the asbestos register. The register and risk assessment then inform the asbestos management plan.

  1. Survey: identifies or assesses suspected ACMs within the agreed scope.
  2. Register: records the known and presumed ACMs and keeps the information current.
  3. Risk assessment: considers material condition and the likelihood of disturbance.
  4. Management plan: defines responsibilities, controls, monitoring, communication and actions.
  5. Review: checks that the information and arrangements are still accurate and effective.

A management survey is commonly used to support normal occupation and routine maintenance. If refurbishment or demolition will disturb areas of the building fabric, a more intrusive refurbishment or demolition survey may be required for the relevant work area. A general management plan does not replace the need to investigate hidden ACMs before intrusive work. Our guide to management surveys versus refurbishment and demolition surveys explains the distinction.

How often should the register and management plan be reviewed?

HSE guidance says the asbestos management plan should be reviewed every 12 months or sooner if necessary. The register should also be updated at least annually as part of that review, and earlier whenever the risk information changes.

An annual review is therefore a minimum management checkpoint, not a reason to wait 12 months after a significant change. Examples that can trigger an earlier update include accidental damage, removal or repair of an ACM, a new survey, changes in access, planned refurbishment, a change in room use or new evidence about a previously inaccessible area.

Common compliance mistakes to avoid

  • Keeping an old survey report but never converting the findings into a working register
  • Treating the survey report itself as the complete management plan
  • Failing to record presumed asbestos in areas that were not inspected
  • Leaving the register unchanged after asbestos is removed, repaired or newly identified
  • Keeping the register in a location that visiting contractors cannot access when they need it
  • Providing asbestos information only after a contractor has already priced or started intrusive work
  • Using a management survey as if it clears an area for refurbishment or demolition
  • Reviewing the documents annually on paper but not checking whether the control arrangements are actually being followed

A practical London dutyholder checklist

  • Confirm who holds the maintenance and repair responsibilities under the lease, contract or ownership arrangements.
  • Check that the survey scope covers the areas you are responsible for and clearly identifies exclusions.
  • Make sure the asbestos register is current, understandable and accessible at the relevant site.
  • Assign responsibility for managing asbestos and identify deputies where necessary.
  • Set a documented monitoring schedule for ACMs that remain in place.
  • Build asbestos checks into maintenance, contractor induction, permits-to-work or other suitable work controls.
  • Review planned refurbishment early enough to commission any additional intrusive survey that is required.
  • Update the register immediately after relevant repair, removal, sampling or building changes.
  • Review the overall management plan at least every 12 months and sooner when circumstances change.

Does every London property need an asbestos register?

No. Regulation 4 is focused on non-domestic premises and the common parts of certain multi-occupancy domestic premises. It does not apply in the same way to the private interior of an owner-occupied home. Responsibility also depends on who has maintenance or repair obligations, so a landlord, tenant, managing agent or other party may hold all or part of the duty depending on the contractual arrangements.

For older premises, HSE advises dutyholders to take reasonable steps to determine whether asbestos may be present and to presume materials contain asbestos unless there is strong evidence that they do not. If you manage commercial property, see our commercial property asbestos management guide.

Authoritative guidance

For the legal framework and current official guidance, consult the HSE duty to manage asbestos guidance, the HSE pages on making an asbestos register and assessing risk, and writing and monitoring an asbestos management plan. The L143 Approved Code of Practice and guidance provides further detail on the Control of Asbestos Regulations 2012.

This article provides general information rather than legal advice. Where responsibilities are unclear, check the relevant lease, contract and maintenance arrangements and obtain competent professional advice where needed.

Need help with asbestos survey information in London?

If you need a survey to support an asbestos register or ongoing management arrangements, see our London asbestos management survey service. For planned intrusive works, review the refurbishment survey service, then request a quotation based on the property, access and the work you intend to carry out.